June 25: Community Road Work Update

TIGER GRANT/Community Road Work

  •  Grading operations will begin near the intersection of Montana Highway 64 (MT 64) and US Highway 191 (US 191). Drivers should plan for reduced speeds, single-lane closures, and delays while grading activities are completed. Grading work will take approximately two weeks to complete, weather and other factors permitting.
  • Concrete crews will complete ADA ramps along the bike path between Andesite Road and Big Pine Drive. The path will be closed in sections as crews while concrete work is completed, minimal to no traffic impacts are expected.
  • Rural Improvement District 395 is scheduled to have Treasure State complete the following work the week of June 24th (Monday through Friday).
    • South Fork – small area milling and asphalt patching and asphalt shoulder repairs
    • Ousel Falls – Town Center – localized milling and asphalt patching
    • Ousel Falls – Town Center to Crown Butte – asphalt overlay
Back to top